The array run has its own rulebook
Most DC circuits in a solar system are sized under Article 210 like any branch circuit. The run from the modules is different: NEC Article 690 governs it, and three things follow from that.
The 125 % on Isc
NEC 690.8(A)(1) defines the maximum current of a PV source circuit as 125 % of the sum of parallel module short-circuit currents. This is not a safety margin you can decide to skip. Real irradiance exceeds the 1000 W/m² standard test condition regularly — snow reflection, cloud-edge focusing and altitude all push modules above their rated Isc.
NEC 690.8(B) then applies a second 125 % as the continuous-duty factor, exactly as it does elsewhere. The combined multiplier on nameplate Isc is 1.5625.
Free air, not conduit
PV wire and USE-2 run openly between modules and racking are single conductors in free air, covered by NEC Table 310.17. Those ampacities are meaningfully higher than the Table 310.16 figures for conductors in a raceway — 8 AWG copper at 90 °C is 80 A in free air against 55 A in conduit.
The moment the run enters conduit, Table 310.16 governs that portion, along with the conductor fill adjustment if there are four or more current-carrying conductors in it.
The rooftop adder
Series wiring is what makes this run cheap
Voltage drop is proportional to current, and current is what series wiring leaves alone.
Take twelve 400 W modules with Isc of 10.3 A and Vmp of 41.5 V, 100 ft from the controller:
- All parallel at 12 modules: 124 A of Isc at 41.5 V. That needs very large conductors.
- Four series, three parallel: 31 A at 166 V. Dramatically smaller.
- Six series, two parallel: 21 A at 249 V. Smaller again.
Same array, same energy, wildly different cable bills. The limit is your charge controller’s maximum input voltage — checked at your coldest expected temperature, because module open-circuit voltage rises as temperature falls under NEC 690.7(A)(1). That check is the job of the charge controller calculator, and it is what stops this optimisation destroying the equipment.
Choosing the conductor type
| Where the run is | Type | Why |
|---|---|---|
| Exposed under the array | PV Wire or USE-2 | Sunlight and moisture resistant, 90 °C wet, and required for exposed single-conductor runs under NEC 690.31(C). |
| In conduit outdoors or buried | THWN-2 or XHHW-2 | 90 °C wet rating. Plain THHN is dry-location only. |
| Inside the building | THHN in conduit | 90 °C dry, the standard interior choice. |
Ordinary building wire outside conduit in sunlight is not acceptable here: UV degrades the insulation and the conductor is not listed for the exposure.
Fusing the array
Two or fewer parallel strings usually need no string fuses at all — with only one other string able to back-feed a fault, the fault current cannot exceed what the conductors already carry. Three or more parallel strings generally do need a fuse per string, and that fuse must not exceed the module’s maximum series fuse rating from the datasheet. The fuse calculator checks that limit explicitly, because NEC 690.9(B) sets a minimum device size and the module rating sets a maximum the code does not license you to exceed.
